Financial results

The financial results are from the Annual Report 2008/09.

Budget

The Net Surplus of $1,665,879 exceeded the budget by $368,789 and is mainly due to decrease in net interest paid resulting from delays in the upgrade work compared to projections. This allowed the NRSBU to use the positive cash flow position to partially fund projects.

The reduced income from Contributors is due to delays in the upgrade projects.

Total expenditure was $854,000 less than budget due to reduced net financing costs, less depreciation than anticipated due to the delay in projects and operational savings, which are passed onto customers under their contracts.

Capital expenditure

Renewal Plan ($,000) Budget Actual Comments
Capital expenditure: Renewal plan
Miscellaneous 20 0 Scada implementation delayed
Pump Stations and Rising Mains 132 2 Replacement of valves not required
Inlet, Aeration Basin, Clarifier and  Ponds 0 0

 

Biosolids tank 0 33

 

Solids Handling 390 0 Not required due to decrease in biosolids produced
Rabbit Island 0 0

 

Roads 19 0 Road upgrade delayed until after completion of upgrade work
Resource Consent 0 3

 

Total = 561 38  
Upgrade Plan ($,000) Budget Actual Comments
Capital expenditure: Upgrade plan
Pump Stations & Rising Mains 4,500 0 Have not received approval from owners to proceed with the project.
Rising Main Study and Strategy 203* 207 * Carry over
Liquid waste receiving facility 371* 340 * Carry over
Bells Island Treatment Plant  
WWTP upgrade 3,581 2,540 Civil and M&E to date
Clarifier scum removal 30 0

 

Outfall upgrade 40 10

 

Biosolids Facility 0 0

 

Total = 8,725 3,125